In this article, the line means sewing production line or production batch. Each line contains a set of machines to make garments for mass production and a set of machines vary depending on product category.
Line planning is scheduling and allocating of orders to production lines according to product setting (product is being made in the line) and due dates of production completion. A line plan defines when a style is going to be loaded to the line, how many pieces to be expected (target) from the line and when an order to be completed. For example, please refer to the following Table-1, where a simple line planning has been shown in a spreadsheet.
During booking orders or allocating orders to the production line, planners must check what is running on the line and how many days it will take to complete the running style.
The benefit of Line planning: It helps the production manager as well as line supervisor with information such as what is the daily production target for a line. They set their line (machines and manpower) accordingly. Line plan also provides information such as how many days style would run, what is the next style going to be loaded?
Table-1: Line Plan
Related Articles:
How to calculate the production capacity of a factory?
Line planning is scheduling and allocating of orders to production lines according to product setting (product is being made in the line) and due dates of production completion. A line plan defines when a style is going to be loaded to the line, how many pieces to be expected (target) from the line and when an order to be completed. For example, please refer to the following Table-1, where a simple line planning has been shown in a spreadsheet.
During booking orders or allocating orders to the production line, planners must check what is running on the line and how many days it will take to complete the running style.
The benefit of Line planning: It helps the production manager as well as line supervisor with information such as what is the daily production target for a line. They set their line (machines and manpower) accordingly. Line plan also provides information such as how many days style would run, what is the next style going to be loaded?
Table-1: Line Plan
Line 1
|
Line 2
|
Total
|
|||
Date
|
Daily
Prod.
|
Cum
Prod.
|
Daily
Prod.
|
Cum
Prod.
|
Daily
Prod.
|
1-Dec
|
loading #2341A,
Qty -3000 pieces |
300
|
1200
|
300
|
|
2-Dec
|
200
|
200
|
300
|
1500
|
500
|
3-Dec
|
250
|
450
|
300
|
1800
|
550
|
4-Dec
|
400
|
850
|
200
|
2000
|
600
|
5-Dec
|
400
|
1250
|
loading #Polo ,
Qty -1500 pieces |
400
|
|
6-Dec
|
400
|
1650
|
0
|
0
|
400
|
7-Dec
|
400
|
2050
|
100
|
100
|
500
|
8-Dec
|
400
|
2450
|
300
|
400
|
700
|
9-Dec
|
400
|
2850
|
350
|
750
|
750
|
10-Dec
|
150
|
3000
|
350
|
1100
|
500
|
11-Dec
|
loading #432K,
Qty -5500 pieces |
400
|
1500
|
400
|
|
12-Dec
|
100
|
100
|
loading #YK45,
Qty -4500 pieces |
100
|
|
13-Dec
|
250
|
350
|
200
|
200
|
450
|
14-Dec
|
500
|
850
|
250
|
450
|
750
|
15-Dec
|
500
|
1350
|
400
|
850
|
900
|
16-Dec
|
500
|
1850
|
400
|
1250
|
900
|
17-Dec
|
500
|
2350
|
400
|
1650
|
900
|
18-Dec
|
500
|
2850
|
400
|
2050
|
900
|
19-Dec
|
500
|
3350
|
400
|
2450
|
900
|
20-Dec
|
500
|
3850
|
400
|
2850
|
900
|
21-Dec
|
500
|
4350
|
400
|
3250
|
900
|
22-Dec
|
500
|
4850
|
400
|
3650
|
900
|
23-Dec
|
150
|
5000
|
400
|
4050
|
550
|
Daily Prod. – Daily production or
line output
Cum Prod. – Cumulative production
of the style till date
|